Use
If you have defined in the Product Master that a product is to be planned manually, you have to create and change all orders for that product manually. You are able to create and change orders from various screens.
If you have defined in the Product Master that a product is to be planned automatically, the system creates and changes receipts automatically to ensure that requirements for these products are covered. However, you are still able to create and change orders for these products manually if you want to improve the planning situation.
You can change both receipts created in APO and receipts that were transferred from the OLTP System to APO.
This procedure tells you on which screens you can create, change and delete orders and what to be aware of on each screen.
Prerequisites
You have maintained all
necessary master data and PP/DS settings.Procedure
Where to Create, Change and Delete a Receipt in PP/DS
Function |
Follow-on menu path |
What you should know |
Create a receipt: |
||
From the initial Production Planning menu |
® Interactive planning ® Create order |
|
|
Choose Create order |
|
On the Product View |
Enter the order data in the elements table. |
You are not able to change the start date of the order when creating an order in this manner. The current date and time is used as the start date for the order. If you wish to create an order with a different start date, create an order by choosing Create order. |
On the Receipts View |
Enter the order data in the receipts table. | |
Change a receipt |
||
Change the quantity or date of date: |
||
On the Receipts View |
Choose Change and change the data in the table |
|
On the Product View | ||
On the Process order screen |
Double-click on Product receipts in the order tree. The Product receipts table appears. |
|
Change source/target location on the Process order screen |
Choose Change in the section of screen entitled Source/Target |
This is the only screen in which you can change the source/target location of a receipt. |
Firm output of receipt on the Process order screen |
Set Output firmed indicator |
Firming the output, means that the order quantity of the product receipt will no longer be changed by the system during planning. You may still change this order manually. For more information, see Firming Orders. |
Delete a receipt |
||
On the Process order screen |
Choose Delete |
|
On the Receipts View |
Select receipts to be deleted and choose Delete at the bottom of table |
|
On the Product View |
Result
Any changes you make to receipts are automatically transferred to the OLTP System.
See also:
Maintaining Requirements