Conversion of SNP Orders into PP/DS Orders 
Use
You use
Supply Network Planning (SNP) for long-term to medium-term aggregated planning. SNP plans based on resources with a period-related available capacity, whereby the smallest possible period is one day. Therefore, you can only plan in SNP within the accuracy of a day and without taking sequence constraints into account. You use Production Planning and Detailed Scheduling (PP/DS) to schedule order dates and resources within the accuracy of a second in the short-term horizon. PP/DS plans on the basis of detailed production process models (PPM) and resources with available capacity that is based on exact times.The
production horizon allows you to separate responsibility for planning. Planning in the production horizon is done in PP/DS, and planning outside of the production horizon is primary done in SNP. If you want to perform detailed planning for SNP receipts in short-term planning, you must plan these receipts in Production Planning and Detailed Scheduling (PP/DS). Within a planning version, you can convert SNP orders that are within or outside of the production horizon to PP/DS orders.You can convert orders as follows:
Prerequisites
To convert orders, you must have made settings for the following master data:
Object |
Settings |
Planning version |
In Model and Planning Version Management you have set the following indicators for the planning version:
|
Resources |
You have assigned the SNP resources and the PP/DS resources to the model of the planning version.
If you want to plan with the same resources in SNP and PP/DS, you use mixed resources for which you can define both an available capacity based on exact times, well as a period-related available capacity. |
PPM |
|
Production horizon |
You have defined a production horizon for the location product as follows:
If you define a product-specific production horizon, the system uses the product-specific production horizon. |
Features
Conversion for In-House Production
If you convert an SNP receipt for in-house production, the system:
Control of Conversion
You can control conversion as follows:
You have the following control options for converting all orders in the production horizon:
Visibility of Converted Orders
SNP orders converted to PP/DS orders are still visible in SNP as aggregated demands. If you use the same resources in SNP and in PP/DS (mixed resources), the resource schedule is visible in SNP and in PP/DS.
Conversion in the Background
You can also convert orders in the background.
Activities
Function |
Menu path |
Converting SNP orders individually |
From the Interactive Production Planning menu area, access the product view for the product. Call the order processing view for the receipt element to be converted.Choose Edit ® Convert SNP order. |
Converting all SNP orders in the production horizon |
From the Production Planning menu area, choose Environment ® Conversion of Supply Network Planning -> Production Planning. |