Detailed Scheduling Heuristics 

Use

The following heuristics, that you can use in the production planning run or in the DS planning board for solving special scheduling tasks, are available for detailed scheduling:

Detailed scheduling heuristics (DS heuristics)

DS heuristic

Use

Schedule deallocated operations

Schedule selected deallocated operations

Lead time reduction

Reduce the lead time for orders that are at selected resources

Backlog rescheduling

Reschedule operations at a resource that lie in the past

Sequencing

Schedule selected operations in a predefined sequence

Manual sequencing

Schedule selected operations in a sequence that was already created manually.

You can only use this heuristic in the DS planning board.

Merging orders on container resources

Merge selected synchronized planned orders at multi resources with storage characteristics ( container resources).

You can only use this heuristic in the DS planning board.

Prerequisites

To be able to call up the heuristics in the menu for the DS planning board under Functions ® Heuristics, you must make these heuristics available in the DS planning board using a heuristic profile. You define heuristic profiles in Customizing for Production Planning and Detailed Scheduling, and you enter the following in Customizing for the corresponding application:

Features

Depending on the heuristic, you can change the selected strategy settings that the heuristic uses to schedule or reschedule operations. Certain strategy settings are permanently set by SAP and cannot be changed.

The system uses heuristics to reschedule operations that start in the planning period.

Activities