Planning Heuristics in Repetitive Manufacturing (REM Heuristics)  

Use

Heuristics serve to solve specific problems within the area of production planning and detailed scheduling.

For planning production in repetitive manufacturing, SAP provides two basic heuristics (REM heuristics; REM = Repetitive Manufacturing). You can change the settings for these heuristics in Customizing, or use them as a template for programming heuristics with your own algorithm (see Setting Up REM Heuristics Create REM Heuristics with your own Algorithm ).

The SAP standard REM heuristics are particularly suitable for planning non-configurable products that are to be produced on simply structured lines (such as filling lines). With these heuristics you can plan several resources (in repetitive manufacturing with PPM) or lines (in REM with iPPE: resources of type line) simultaneously. In this way you can produce products on alternative resources (lines), and load them as you wish within finite planning.

For planning configurable products, a special planning run is available within model mix planning with a special heuristic. For further information see Model Mix Planning Run.

Integration

You can use the REM heuristics the following scenarios:

The heuristics can be used both in interactive planning and background planning.

Prerequisites

Complex iPPE line networks cannot be planned with these REM heuristics. With line networks that consist of several lines, the system always plans the last line.

You cannot plan final products and dependent assemblies at the same time. If you plan the finished products, the dependent requirements for the assemblies can only be taken into account in a subsequent heuristic run.

Features

The following REM heuristics are contained in the SAP scope of delivery:

In this heuristic, the resources are loaded as evenly as possible.

In this heuristic, resources that are defined as primary resources (the preferred resource) are loaded first of all. Planned orders are not moved to the alternative resources until these resources are at full capacity.

Both SAP REM heuristics initially carry out the net requirements calculation, then calculate the lot sizes according to the settings in the product master and finally create scheduled APO planned orders for the available requirements, taking into account the free resource capacity available per period. Depending on your settings, the periods could be daily, weekly, or monthly. User-defined time periods are also possible.

To determine the requirement quantities and dates for the necessary components, the REM heuristics then carry out a single-level individual explosion of the iPPE data, or the production process model and thus determine the dependent requirements for the BOM level directly below.

The heuristics only work with firm setup times and do not take into account sequence-dependent setup, as defined in the setup matrix of the production process model.

Activities

You can start the planning run with REM heuristics in the following applications:

See also:

Production planning run

Heuristics .