Consistency Check 

The consistency check can be carried out at two different points in time.

A dialog box appears displaying the following message:

The consistency check applies if, for example, requirements are to be transferred but you did not consider the appropriate material master when you selected filter objects.

The following list indicates what each filter object is being checked for:

Filter Object

Contained in integration model?

Material

Plant

Production Process Model (PPM)

Material master, resource

Resource

Plant

Plant

Is the time zone maintained?

Customer

Is the time zone maintained?

Supplier

Is the time zone maintained?

Stock

Material master

Special stock at customer

Customer

Special stock at supplier

Supplier

Planned independent requirements

Material master

Purchase order

Material master

Planned order

Material master

Sales order

Material master

Material consumption data

Material master

Production campaign

Material master, production order

Manual reservations

Material master

Production order

Material master

ATP check for materials

Material master