Use
With this function you can carry out automatic planning over a large planning period, which you divide into several planning horizons.
In this way you can gradually increase the level of detail of the planning by using procedures of varying complexity in the corresponding planning horizons. The gradual planning could take the following form, for example:
Integration
Customizing
You define the composition of the planning run in Customizing for model mix planning in a procedure package. Here, you enter the individual procedures and determine the length and number of planning horizons. You assign any procedure to each horizon. You can also determine the following functions:
Using the adjustment periods between the procedures, you can allow the planning horizons to overlap. Then the system transfers the orders that it scheduled at the end of a planning horizon to the next planning horizon and thus the next procedure. This makes sense, as the orders from a procedure that cannot be brought into a permitted sequence, are scheduled at the end of the planning horizon.
If you do not want to make any more changes in the short-term horizon, you can enter a planning offset in the procedure package. Then you can start the first horizon of the planning run starting from the current date, delayed by a few days or shifts.
The
For the prioritized equal distribution and the genetic algorithm, you can create a processing profile in Customizing for model mix planning. You then enter the processing profile in the planning horizon.
Heuristics
You can start the planning run manually or schedule it as a background job. In addition, you can integrate the model mix planning run as a heuristic in the production planning run of the APO System. For example, you can carry out a planning run every night, and thus periodically update your planning.
See also:
Integrate as Heuristic in Production Planning Run.Prerequisites
Features
If you start the planning run, the system processes the horizons per time period, beginning with the short-term horizon. It deals with each horizon in the following way:
Depending on the planning basis you have set in the procedure package, the system only considers:
In this case you display the planning result in the
In this case you display the planning result preferably in the interactive
Example
The following diagram displays a possible planning run with three procedures that SAP delivers as standard: