Use
There are two types of automatic planning in Production Planning and Detailed Scheduling: Automatic planning immediately and Automatic planning in a planning run.
You can define how the product is to be planned on the PP/DS tab of the product master. Both types of automatic planning are triggered when:
Integration
The orders created during automatic planning are immediately
transferred to the connected OLTP system so that up-to-date planning data is available in both systems.
Prerequisites
You have set either the Automatic planning immediately indicator or the Automatic planning in the planning run indicator in the product master (PP/DS tab) for the product. If you wish to check the availability of components of the product, you must also set the Automatic planning immediately indicator.
Features
Automatic Planning Immediately
Products are planned immediately when automatic planning is triggered. The system performs an availability check for a product and its components. If a product is not available, it automatically creates suitable receipt elements while taking resource capacity into account. The system selects the procurement alternative according to priority and costs that can fulfil the order on the requested date. For more information, see
Automatic Planning Immediately.Automatic Planning in the Planning Run
When changes relevant to planning occur, a planning file entry is created. These products are then planned during the next net change production planning run using the
heuristic defined for the product in the product master or, if you have not defined a heuristic here, the default heuristic from the global settings in Customizing is used. A variety of heuristics are available for Production Planning that can be used to plan products. For more information, see Automatic Planning in a Planning RunFor more information on the production planning run, see
Production Planning Run.