Order Processing View 

Definition

Screen in Production Planning and Detailed Scheduling for displaying and processing an order.

Use

In the order processing view, you can create, change or delete an order. You create receipts for components for which you have defined manual planning in the product master. You can use product heuristics to improve planning for the components. In the order processing view, you can display the order in its environment, which includes:

Structure

The order tree is displayed on the left side of the order processing view. It consists of the order as the top node, as well as subnodes under which the actual order objects are listed.

Elements of the Order Tree

Subnodes

Order objects

Receipts

Products of the order

Requirements

Components of the order

Operations

Operations and activities of the order

 

By double-clicking an element of the order tree (node or order object) you control the content on the right side of the order processing view.

 

Content of the right screen area after double-clicking a node

Node

Content of the right screen area

Order

Header data of the order such as dates, alerts and status information

The APO System displays the status of the order according to the status change made in the integrated OLTP system (for example, released or confirmed).

On this screen you can:

The APO System automatically sets the Input firmed indicator when you manually change the quantity of a component.

Receipts

List of order products with the detail data, such as the availability dates and quantities.

Reqmts

List of order components with the detail data, such as the requirements dates and quantities.

Operations

List of order operations with the detail data, such as dates and quantities.

 

Content of the right screen area after double-clicking an order object

Order object

Content of the right screen area

Order product

Component

Product view, plus the following tabs:

  • The Alternatives tab contains the options for external procurement of the order product or the components. You can enter alternative quantities and availability dates for the procurement options and have the system perform a product availability check. You can create orders for alternative procurement options.

Operation

Operation data, for example, resources being used, input and output products and relationships

Activity

Activity data

 

Integration

Calling the Order Processing View

You can call the order processing view either:

Detailed Scheduling Strategies

The system performs detailed scheduling for an order using the detailed scheduling strategy you have specified under Settings.

Alert Monitor

The display of alerts for quantity and date problems are integrated in the order processing view. To display further alerts, for example, for resource problems, you can call up the Alert Monitor.

Plan Monitor

To display the quality of the planning based on your own criteria, you can call up the Plan Monitor.

DS Planning Board

To display the schedule of the orders in a Gantt chart, you can call up two differently configured DS planning boards from the order processing view. Here you can manually reschedule orders or call the optimizer.