Use
The integration of the location product is described below.
Integration
The SAO APO location product is supplied with plant material data from the SAP R/3 System.
The partial areas planning strategy and dependent requirements are supplied from the SAP R/3 system; dynamic pegging can only be maintained in SAP APO.
The parameters for calculating the lot size and the days’ supply determination are copied from the SAP R/3 System (this corresponds to the lot size data in SAP R/3).
You can maintain this data entirely in SAP APO, with the exception of the purchasing group for which the data was taken from the SAP R/3 System.
All fields in this tab page are SAP APO fields and are only maintained in SAP APO.
The parameters for procurement type, planned delivery type, goods receipt and goods issue data are taken from the SAP R/3 System; you can maintain the remaining data in SAP APO.