Use
You can use this
heuristic to reschedule the backlog in the production planning run and in the
DS planning board; that is, you can automatically reschedule the operations that lie in the past in the
planning period to the current date or in the future.
Features
The current date and current time is the default for the earliest possible start date for the operations to be rescheduled. With the help of the offset time in the heuristic settings, you can shift the earliest possible start date into the past or into the future.
This heuristic uses the function module /SAPAPO/HEUR_RESOLVE_BACKLOG.
For more information regarding prerequisites and activities for using the detailed scheduling heuristics, see