Use
You use
Fixed Pegging if you wish to fix the assignment of a receipt element to a requirement element and if the system should not change this assignment during planning. The following pegging types exist:You can
In the following cases, the system can fix pegging relationships automatically:
If you have determined in the location product master for a product that the dependent requirements for the product should be planned as an order network, the system does not use existing receipt elements to cover the dependent requirements. Instead it creates exactly one receipt element with the required quantity (exact lot size) for each dependent requirement and assigns it to the requirement element. The system fixes this pegging relationship automatically.
You can determine if the system should create a pegging relationship in a
Fixed pegging relationships cannot be transferred to an OLTP system.