Entering content frameBackground documentation Budget Allocation Prerequisites Locate the document in its SAP Library structure

The following settings determine whether a budget can be allocated to a WBS element or an order:

You store a budget profile or order type in the project definition. This profile contains the control parameters for budgeting. In Customizing, under Project System ® Costs ® Budget ® Define Default Budget Profile for Project Definitions you define:

The following are additional ways in which you can assign a budget profile to a project:

You can allocate budget after the status Created has been reached. If you want to prohibit budget allocation in the Created status, you need to define a user status.

For more information on status management in the project system and for internal orders, and on how to create a user status, see Structure linkStatus Management or status management for internal orders.