Entering content frameProcedure documentation Exploding the Bill of Material Locate the document in its SAP Library structure

Use

If you have allocated a material with a bill of material (BOM), a sales order BOM, or a WBS BOM to an activity, you can explode this BOM in the network level-by-level or completely (multi-level).

You need to explode a bill of material, if

For more information, see Structure link BOM Explosion

 

If the material component was already allocated to the activity before the BOM explosion, you have the following options.

Procedure

  1. On the Component Overview screen for an activity, choose Components ® Explode BOM.
  2. The BOM selection dialog box appears.

  3. Enter the necessary data, for example for a WBS BOM the WBS element for which the BOM was created. The default value for the requirements quantity is the Structure link Execution Factor in the activity. You can explode the BOM level-by-level or all at once (multi-level).
  4. Caution

    If you explode the BOM all at once, requirements could be generated both in the network and in MRP, depending on control of the BOM items. Since MRP always explodes the complete BOM, this could lead to multiple requirements for the same component.

  5. Choose Continue.
  6. A list of all the BOM items appears. You expand or compress multi-level BOMs by choosing This graphic is explained in the accompanying text or This graphic is explained in the accompanying text. Choose This graphic is explained in the accompanying text to display the BOM as an overview tree of the BOM structure in which phantom assemblies are shown as such.

    Note

    Document items are not displayed, since the system does not copy document items to network activities.

  7. Select the items that you want to allocate to the network in the list or the tree and choose Copy.
  8. If necessary, check the data for inventory management and account assignment.
  9. Save the network.

See also:

BOM transfer

 

Leaving content frame