Entering content frameFunction documentation Material Assignment to Standard Networks Locate the document in its SAP Library structure

Use

In standard structures you can predefine material assignments by assigning material components to the activities of a standard network.

When you create a network by using a standard network as a template, the system automatically copies the material assignments.

If you use a standard network as a template for a new standard network, the system also automatically copies the material assignments, except those assigned via a standard BOM.

Prerequisites

In contrast to operative networks, you can assign material components to a standard network, if they belong to a BOM.

If a BOM does not already exist, you must create a normal BOM or a so-called standard BOM first. Both standard and normal BOMs are always defined for a plant; if you want to assign materials from different plants, you need a BOM for each plant.

A standard BOM does not have a "header material"; it is an aid that is just used for assigning material to one standard network.

Activities

See also:

Assigning Material Components to Standard Networks

Creating a Standard Bill of Material for Assigning Material to a Standard Network

 

Leaving content frame