Entering content frameFunction documentation Procurement via Materials Requirements Planning Locate the document in its SAP Library structure

Use

If you allocate a material with the item category L and the corresponding settings in the material master to a network activity, the system generates a reservation for the material. A reservation is an internal document that defines the requirements of a material and reserves a specified quantity for the network activity.

The material is procured using material requirements planning (MRP). For more information on requirements planning, see the Structure link Requirements Planning (PP-MRP) component.

This graphic is explained in the accompanying text

As soon as the reservation is activated, the systems carries out an availability check for the material in the next MRP run. If there is not enough material in stock to meet the requirements, the system creates a Structure link planned order. Planned orders can be converted into production orders for the actual manufacture of the material component required or into purchase requisitions/orders.

This graphic is explained in the accompanying textIf a purchase requisition is generated the same process takes place as described in the graphic in Direct Procurement.

If you use MRP, you still can decide whether to manufacture a required material internally or to buy it from an external vendor. However the decision will then be taken an MRP controller, who depending on your orgnization structure and the kind of material involved, may not be directly involved with your project.

 

Leaving content frame