Process Flow
In this example, a quantity of 10 pieces is entered with a required delivery date of today. An order like this can be confirmed after the replenishment lead time.
Stage 1: Demand Management
This stage does not apply to this strategy.
Stage 2: Procurement Before Sales
This stage is also not applicable in this strategy because production does not take place without a sales order. If there are advance sales orders in the system, production is carried out before the required delivery date.
Stage 3: Sales Order
Here you need to note the following:
· It is possible to confirm a quantity according to an ATP checking rule ( Edit ® Check availability on the Sales Order screen). Here it is important that you maintain the material master so that the replenishment lead time is used in the check, because you do not always have warehouse stock.
· The system finds the schedule line category CP and the item category TAN because the item category group was set to NORM. The
· The system finds the requirements type KL (under the Procurement type tab title) because the strategy group has been set to 30.
Date |
MRP element |
Received/ |
Available quantity |
<today> |
Stock |
0 | |
<today> |
Order |
10 - |
10 - |
Stage 4: Procurement After Sales
Date |
MRP element |
Received/ |
Available quantity |
<today> |
Stock |
0 | |
<today> |
Order |
10 - |
10 - |
<t + rlt> |
PlOrd. |
10 |
0 |
Make-to-stock + rlt = today + replenishment lead time
This procurement requisition is the starting point for production or external procurement. Various possibilities exist for handling the procurement process in the R/3 System. One option would be to convert the planned order into a production order, then release the production order and a goods receipt of the yield quantity. It is also possible, however, to use returns or other goods movements for make-to-stock production.
Date |
MRP element |
Received/ |
Available quantity |
<today> |
Stock |
10 | |
<today> |
Order |
10 - |
0 |
Stage 5: Goods Issue for Delivery and Reduction of Planned Independent Requirements
After delivery (Logistics ® Sales and distribution ® Shipping ® Delivery ® Create) and goods issue, the stock/requirements list is reset to initial (empty).