Materials in Projects 

Technical name: SAP_PS_MATERIAL

Tasks

You can use the transactions for this role to plan and monitor project material requirements and costs, and to regulate and schedule the flow of materials.

Activities in the Project System

Transaction

Function

MM01

Create Material

MM02

Change Material

MM03

Display Material

CN33

BOM Transfer

MD51

Project Material Requirements Planning

MD50

Sales Order Material Requirements Planning

MD4C

Order Report

CO46

Order Progress Report

CO24

Backlog Processing: Missing Parts Information System

CO06

Backlog Processing: Materials

V_RA

Backlog Processing: Sales Orders

MDUP

Sales Order/Material Assignment: Edit

MDUS

Sales Order/Material Assignment: Display

CNL1

Create Delivery Information

CNL2

Change Delivery Information

CNL3

Display Delivery Information

CNSO

Delivery from Project