Posting Goods Issue for Reservation of the Network 
Usage
The component produced was posted automatically to the project stock when the production order was finally confirmed. When the bill of materials (BOM) was assigned, a corresponding reservation for the activity was created. If the component is required, goods are withdrawn for the reservation.
Procedure
Menu Path |
Logistics ® Materials Management ® Inventory Management ® Goods Movement ® Goods Issue |
Transaction Code |
MB1A |
Field |
Data |
Movement type |
101 |
Plant |
1300 |
Storage location |
0001 |
Field |
Data |
Network |
First network for your project T-10## |
The component is posted to the goods issue document.
Result
The goods issue is posted. The project stock is reduced and the reservation is reduced to zero by the activity.
Switch to session three Stock/Requirements or call up the current
Stock/Requirements List again. To evaluate the current data, chooseThe components are taken from the project stock via the goods issue for the reservation. This leads to a credit of WBS element T-10### and of the activity. On network activity 4100 "Production of runners/rotors and bearing boxes, (cum.)", the actual costs are posted using consumption cost element 890000. The stock value of the WBS element under cost element 790000 Unfinished Products is reduced accordingly.
Switch to session two Cost Report, or call up the
cost element report again. To evaluate the current data, choose