Assessment 

Purpose

Assessment is used to allocate planned or actual costs. The costs are allocated from cost centers to receivers. These receivers could be other cost centers, orders, projects and so on.

This process shows assessment of the plan costs. You see how to define an assessment cycle and how the costs are then allocated. Actual costs are assessed in the same way, except that a different assessment cycle is used.

You can find more information about this process under .

Process Flow

You can find the data for this process under .

  1. Displaying a Cycle for Assessment
  2. Executing Assessment
  3. Displaying the Results in Reporting