Usage
To check whether you can deliver the turbines on the date agreed, you schedule your project according to that date.
Procedure
Menu Path |
From the Project node, choose Project Builder. |
Transaction Code |
CJ20N |
The system displays your project in the Preview, as set up for your user.
The work area displays the detailed data for the project definition.
Field |
Data |
Finish date |
Today's date + 1.5 years |
The system expands the project structure.
The project planning board appears. The project planning board offers you a graphical interface for the planning and monitoring of the dates of the WBS elements and activities.
The Change Standard Values in Project Planning Board dialog box appears.
Field |
Data |
Schedul. method |
WBS determines dates |
The system selects all of the project objects.
Starting with the final date for the project, the system determines the earliest and latest dates for the activities, and displays the schedule situation.
The system transfers the maximum scheduled dates (earliest start and latest finish) for the activities to the WBS elements, and extrapolates the dates in the project structure.