Show TOC
Primary Costs and Business Processes
Scope of Functions
The uses for business processes have been extended; you can enter
primary costs through primar cost elements in business processes.
Following are the new uses:
- Together with the actual booking of a document on the financial
accounting side, you will also be able to enter data directly in the respective business process.
- If you want to enter a purchase requisition or an order for a business
process, you can carry out the corresponding account assignment for each material item.
- With inventory management, you can book a material receipt for a specific business process.
- With business process planning, you can enter not only the use of
activities or other processes, but also fixed and variable primary cost
centers over the corresponding cost elements. To support the planning,
you can also use planning aids such as formula planning, plan revaluation, plan reconciliation and plan copying.
An account assignment in the business process is also prossible with the following manual actual bookings in controlling:
Note
- An account assignment from HR costs in business processes is not possible.
- Business processes cannot be booked with with revenues (for example, down payments, invoices).
Effects on Customizing
To make account assignments of business processes through G/L account
postings in FI, indicate the G/L account and booking keys "business process" as entry field in
To enable the account assignment in materials management, you must set the business process as Possible entry:
See also
For more information, see the SAP Library under AC-Accounting -> CO-Controlling ->
Overhead costs-Controlling -> Activity-Based Costing -> Process planning -> Manual process planning ->
Planning process input.