Inclusion of Valuation Variant in Manual Activity and Process Allocation

Scope of Functions

In earlier releases, valuation was always performed on the basis of the planned activity price of the current period in the following cases:

In Release 4.6A, valuation in simultaneous costing in Cost Object Controlling in accordance with the valuation strategy specified in the valuation variant is performed when:

A requirement is that the receiving object has a costing variant for simultaneous costing. This is not the case, for example, for production orders without a quantity structure (CO production orders).

See also

For information on the use of valuation variants in planning and allocation for business processes, refer to the Release Note Linkage of Business Processes to Valuation Variants