Determining the Procurement Proposal 

Implementation Options

Procurement proposals are used to procure the shortage quantity. Procurement proposals are internal planning elements that can be changed, rescheduled or deleted at any time: purchase requisition and planned order. In contrast, delivery schedule lines are fixed elements, which must be followed, and are only part of the procurement proposals in a broader sense.

Process Flow

If you create a planned order in external procurement first, this has the advantage that the MRP controller has more control over the procurement proposals. Only once the MRP controller has checked the planned orders and converted them into purchase requisitions can the purchasing department order the material. Otherwise, the purchase requisition is immediately available to the purchasing department, which then takes over responsibility for material availability and warehouse stocks.

For more information, refer to MM - Purchasing under:

Scheduling Agreement

Source List