Calculating Scrap 

Use

You can calculate and plan the scrap quantity that will result from production. These scrap quantities are then included in the planning run and in the calculation of production costs.

Prerequisites

Which calculation the system uses depends on the settings in the material master record or in the BOM.

Features

The scrap quantity is settled against the net requirements quantity.

Three calculation procedures are supported by the system: