Calculating Procurement Quantity
Implementation Options
The system calculates procurement quantities in MRP. The system determines material shortages for requirement dates in the net requirements calculation. Receipts must now cover these shortage quantities. The system calculates the receipt quantity in the lot-size calculation, which is carried out during the procurement quantity calculation.
Prerequisites
Process Flow
Result
The system uses the result of the procurement quantity calculation as the quantity for production or procurement of the material. This is made up of the estimated yield and scrap. You can display and change the procurement quantity in the procurement proposal. The estimated yield and scrap are displayed in the MRP list and the stock/requirements list.