Consumption-Based Planning 

Use

As the name suggests, consumption-based planning procedures use past consumption data (historical data) to calculate future requirements with the help of the material forecast or static planning procedures. Consumption-based planning procedures have no reference to the master plan. This means that the net requirements calculation is not triggered by an independent or a dependent requirement. Instead, the net requirements calculation is triggered when stock levels fall below a reorder point or by forecast requirements calculated from past consumption data.

The advantage of this type of planning is that it is easy to use and you do not require extensive data.

Prerequisites

Features

The MRP procedures supported in consumption-based planning are:

See also:

Forecast Parameters

Significance of the Material Forecast for Materials Planning