Completing the Notification 

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Quality Management ® Quality Notification ® Change

    Transaction Code

    QM02

  3. On the initial screen, enter the number of the notification you last processed and choose Notification.
  4. Choose (Complete).
  5. A dialog box appears, in which you must specify whether the problem was caused internally or externally.

  6. Accept the External origin proposal.
  7. The quality problem was caused by the vendor, so the problem notification goes into the vendor evaluation.

  8. To complete and save the notification, choose .
  9. Choose .

The notification can no longer be changed, only displayed.

Reversal

  1. If you accidentally completed the notification before it was necessary, call up the following transaction:
  2. Menu Path

    Logistics ® Quality Management ® Quality Notification ® Change

    Transaction Code

    QM02

  3. On the initial screen, enter the number of the notification you last processed and choose Notification.
  4. Choose Notification ® Functions ® Put in process.

Now you can make changes to the notification.