Basic Settings for Availability Control in Budget Profile 

Use

In the budget profile you determine whether/how availability control is to be activated and which budget values should be checked by availability control.

Features

You control whether/how availability control should be activated using activation types (0=not activated, 1= Automatic Activation with Budget Allocation, 2= Backround Activation).
More information is available in
Activating Availability Control.

For projects, availability control can check against the current budget or the released budget. Furthermore, you can decide whether availability control is carried out on the basis of year-independent (= total values) or year-dependent values. Depending on the settings of the budget profile, the availability control checks against the

The current budget is made up of