Processing of Inspection Plans/Reference Operation Sets 

Purpose

You use inspection plans to process a quality inspection in Quality Management (QM). You use reference operation sets as copy models or references.

Prerequisites

Process Flow

  1. You call up the transaction for processing task lists and select a working area.

If you work with user-specific roles, the work area screen is not displayed. Instead, a selection screen appears.

You can use the same transaction for creating, changing or displaying a new object (for example, task list header, inspection characteristic, test equipment).

You enter the selection period and the selection criteria for the objects to be displayed or processed. There are two screens available with different selection criteria for this selection.

If you want to change existing objects, you must enter a change number in the screen section Process using.

If you change existing objects, these objects are loaded from the database into your worklist and are locked against the access by other users (indicated by the lock symbol).

  1. You switch to the required level of the object (for example, task list header level, operation level inspection characteristic level).
  2. If you want to create a new object, enter a key for the required object in the context block.

  3. You process the header data in the inspection plan or reference operation set.
  4. You process the inspection operations in the inspection plan or reference operation set.
  5. You assign inspection characteristics to the inspection operations.
  6. If necessary, you perform the following steps (in any order):
  1. You release the inspection plan or reference operation set.
  2. You save the inspection plan or reference operation set.

If you want to delete an inspection plan or reference operation set, in the task list overview, select the inspection plan or reference operation set to be deleted and choose Delete.