Make-to-Order Production w/ Configuration (25) 

Purpose

This strategy, similar to Make-to-Order Production (20), is used when planning of the parent product is not required or not possible. Components must be planned by other means, if necessary.

This strategy is used for configurable materials. Configuration is required.

Prerequisites

You must maintain the following master data settings

Process Flow

  1. Stage 1: Demand Management
  2. Does not apply.

  3. Stage 2: Procurement Before Sales
  4. Does not apply.

  5. Stage 3: Sales Order
  6. You enter the variant material and its configuration. The default combination values apply and can be used as the default configuration.

  7. Stage 4: Procurement After Sales
  8. Variant material is produced.

  9. Stage 5: Goods Issue for Delivery and Reduction of Planned Independent Requirements

Goods Issue for the configurable material takes place.

See also:

Comparing Strategies 25 and 26