Scheduling with Maintenance and Service Orders
Scope of Functions
In Release 4.6A, maintenance and service orders incorporated into a
project as a subnetwork can be included in overall network scheduling and WBS scheduling.
There is a new field controlling integration, which stipulates the objects you want to schedule.
- Maintenance and service orders only, if the networks have already been scheduled
- Networks and maintenance and service orders
In this case, the network is scheduled first. The scheduled activity
dates are copied to the header of the maintenance and service orders; these orders are then scheduled using the header dates.
If errors occur during maintenance/service order scheduling, the system displays them in a scheduling log.