Consider Backlog in Capacity Availability Check

Scope of Functions

As of Release 4.6A, you can consider the backlog in the capacity availability check; that is, the capacity requirements of operations that lie in the past.

In doing so, the system loads all the capacity requirements into the today's date period that lies between the start of the time period for reading the database and today's date. During the check and during finite scheduling in the capacity availability check, the system assumes that the today's date period and the subsequent periods are loaded by the backlog capacity requirements - up to the maximum load limit for the capacities.

If the system has to consider the backlog during the capacity availability check, you must enter in the overall profile for capacity leveling and extended evaluation the settings that you want to use for the capacity availability check. These are as follows: