External Services Management (MM-SRV) 

This section provides a general introduction to MM External Services Management.

It provides an overview of the functionality, shows how MM External Services Management is integrated into the Purchasing application within the Materials Management module, and indicates the interfaces to other applications.

Purpose

MM External Services Management (MM SRV) is an application component within the Materials Management (MM) module. It supports the complete cycle of bid invitation, award/order placement phase, and acceptance of services, as well as the invoice verification process.

Features

MM External Services Management provides a basic process for the procurement of externally performed services. This basic process comprises the following functionality:

By "planned services" we mean services whose nature and scope is known to you at the start of a procurement project or transaction.

At the time the services are requested, the individual specifications are entered either with the aid of a service master record or directly as short and long texts. Price and quantity are specified in both cases.

By unplanned services, we mean services that cannot be specified in detail because their precise nature and scope are not initially known, or services which - for various reasons - you do not wish to plan. Unplanned services therefore have no descriptions.

They are entered in the form of monetary limits. Services may be performed up to a value not exceeding these value limits. This allows you to exercise a degree of cost control in such situations.

As an alternative to this basic process, various accelerated and simplified processes are made available to you for use if desired in connection with specific procurement transactions.

Integration

MM External Services Management is completely integrated into the Materials Management system. The master data for the procurement of services can be stored in service master records, for example, which subsequently provide default data for the purchasing documents. Service specifications for a concrete procurement project are not created and processed separately each time (e.g. as bid invitation or contract specifications), but entered directly in the purchasing documents (e.g. in a request for quotation, quotation, purchase order or contract).

The following graphic demonstrates the degree of integration of MM External Services Management:

The External Services Management component is linked to the SAP modules PM Plant Maintenance and PS Project System. As a result, it is possible to create purchase requisitions for external services within the framework of maintenance measures or a project and then transmit them to Purchasing without incurring additional data maintenance work.

The interaction of the R/3 modules MM, PS and PM, CO and FI saves time and effort and reduces the frequency of errors. This is because data need be entered once only, after which it is available for all follow-on activities within a business process.

An example of the integration of MM and CO is purchase order commitments. The expected value of unplanned services is forwarded to CO from within MM so that a commitment figure can be established and monitored. This enables the relevant budget for procurement measures to be prepared in good time.