Integration with Materials Management 
Use
Business transactions posted in Materials Management are updated in Funds Management. The following business transactions can be updated in Funds Management:
Purchase requisition, purchase order, scheduling agreement
Goods receipt, goods issue, transfer
Invoice receipt, logistics invoice verification
Irrelevant postings
You can use the appropriate Customizing settings to specify that no updating takes place in Funds Management for unassigned purchase orders and purchase requisitions as well as for goods issue. You enter this setting in the Funds Management Customizing work step Enter other settings.
If other business transactions from Materials Management are not budget relevant for you (e.g. purchase orders), you can define per value type in the Funds Management IMG in the workstep Override update profile, that the update is only statistical. The
statistical postings are displayed separately in the information system.Apart from this, you can prevent updating for individual line items that are irrelevant to Funds Management by entering a commitment item that does not have the
Financial Transaction 30. This is only possible for postings for which you either enter a commitment item manually or for which you can change a commitment item that the system automatically recommends.Prerequisites
Prerequisites for Updating in Funds ManagementFeatures
Unassigned purchase orders/purchase requisitions
You define how updating of unassigned purchase orders takes place depending on which Warehouse Concept is relevant for you. If budget is available to the warehouse itself by way of a warehouse funds center, you must stipulate that unassigned purchase orders are posted automatically to this warehouse funds center. The system usually determines the commitment item automatically as a default value from the G/L account addressed by the MM account determination.
You must define that unassigned purchase orders are assigned to an account manually if the budget is not to be managed via a warehouse funds center. If you are entering an unassigned purchase order (such as a purchase order to stock), a screen in which you can enter a funds center and a fund follows the detail screen . The system usually determines the commitment item automatically as a default value from the G/L account addressed by the MM account determination.
You can change or display the FM account assignments in the item overview by choosing Item ® Additional functions ® Cash Budget Management.
Assigned purchase orders/purchase requisitions
For updating assigned purchase orders and purchase requisitions a complete FM account assignment must be included when posting. You either make the inclusion manually or according to the assignments made from commitment item to G/L account or FM account assignments to CO account assignments. Weitere Informationen finden Sie unter FM Account Assignment Logic und Field Status Customizing.
You can enter multiple account assignments for assigned purchase orders - that is, you have the option of distributing the amounts for a purchase order item to more than one funds center or commitment item.
Depending on the settings you have made for the assignment screen, you can use the field More to reach a second overview screen, in which you can enter budget relevant account assignments.
Time when the purchase order commitment is redeemed
You can choose to redeem the purchase order commitment either at goods receipt or at invoice receipt. You enter this setting in the Funds Management Customizing work step Enter other settings.
If the purchase order is redeemed at goods receipt, then the goods receipt is displayed in the information system under the business transaction "Invoice". Otherwise the goods receipt is not displayed.
Note the following special features:
In cases of underdelivery or overdelivery, you must, in accordance with the Customizing settings you entered:
These indicators show that the purchase order item is regarded as completed; the corresponding purchase order commitment is reduced to zero. The "Invoice" business transaction in the information system shows the amount that was posted in the goods/invoice receipt.
If you do not set the final delivery/final invoice indicator, the amount posted when goods or the invoice are received appears under "Invoice"; "Purchase order" continues to show the difference between the original purchase order and the goods/invoice receipt.
Value-Based Commitments
By choosing Check units of measurement in the Global settings Customizing, you can set a " Value-based commitment" indicator. This indicator controls whether commitments for the chosen unit of measurement or unit of measure are recorded on a quantity basis or a value basis.
If you do not set the indicator then the commitments are managed on a quantity basis. If you set the indicator they are managed on a value basis.
If you have specified in Customizing that units of measure are to be recorded on a value basis, you must, in accordance with the settings you chose when the purchase order commitment was redeemed (goods receipt or invoice receipt):
If the invoice amount is less than the purchase order amount and you do not set the final delivery/invoice indicator, "Purchase order" in the information system continues to show the difference between the two amounts.
Parked documents
Parked documents are only updated if they have the status " Complete". Updating is always net irrespective of whether you have chosen the setting Gross or Tax separate.
Activities
You enter the required settings, in order to control updating of posting data from Materials Management in accordance with your requirements, in the Funds Management Customizing in the work step
Make other settings.
See also:
Overview of Posting Ex. Consumable Materials/Warehouse Concepts Posting Example for Consumable Materials Posting Example Warehouse Concept 1 Posting Example Warehouse Concept 2 Posting Example Warehouse Concept 3 Posting Example Warehouse Concept 4