Creating Production Orders Without a Material 

  1. Choose Logistics ® Production ® Shop Floor Control ® Order ® Create ® Without material.

You reach the initial screen Create production order.

  1. Enter the following data:
  1. You must also specify the following data:

If you want to create the order with reference to an existing order then the order referenced must also be one without a material.

  1. Choose .
  2. The General tab page appears.

  3. Enter the following data:

Production orders are generally scheduled backwards.

If you specify a scheduling margin key the system fills these fields automatically.

If no scheduling margin key has been specified you can specify the float before production, the float after production and the release horizon by specifying the corresponding number of days.

  1. You must also specify the following data:
  1. Choose .

You reach a dialog box where you can specify whether you want to use a reference operation set. If you do not want to use a reference operation set then a standard sequence is automatically generated with an operation.

The system searches for a valid routing (see Routing Selection) and a valid bill of material (see Selecting Bills of Material).

If alternative sequences exist in the selected routing, they can only be copied to the production order if alternative sequences are permitted for the order type in Customizing for Shop Floor Control: Choose Master data ® Order ® Define Order Type-Dependent Parameters.

If you do not want to change the operations or add any components, you can now save the production order. Otherwise, change the data and then save the production order.