Creating a Production Order with a Material 

  1. Choose Logistics ® Production ® Shop Floor Control ® Order ® Create ® With material.

You reach the initial screen Create production order.

  1. Enter the following data:

You can use the planning plant for example when you have organized sales as an independent plant. However, in most cases the production plant and the planning plant are not identical. If both plants are identical you only have to specify a plant number. The other number is then filled automatically.

  1. Choose .
  2. You reach the tab page General.

  3. Enter the following data:

If a fixed lot size is specified in the material master for the material to be produced (MRP) then the lot size is proposed as the order quantity in this field.

Production orders are generally scheduled backwards.

If you specify a scheduling margin key the system fills these fields automatically.

If no scheduling margin key has been specified you can specify the float before production, the float after production and the release horizon by specifying the corresponding number of days.

  1. You must also specify the following data:
  1. Choose .

The system searches for a valid routing (see Routing Selection) and a valid bill of material (see Selecting Bills of Material).

If alternative sequences exist in the selected routing, they can only be copied to the production order if alternative sequences are permitted for the order type in Customizing for Shop Floor Control: Choose Master data ® Order ® Define Order Type-Dependent Parameters.

If you do not want to change data copied from the routing or bill of materials then you can save the production order now. Otherwise, change the data and then save the production order.