Convert Planned Order Into Production Order and Release 

Use

You convert a planned order into a production order and trigger the production of an engine.

Procedure

  1. You are in the Stock/Requirements List as of XXX Hrs.
  2. Choose in the row of the first planned order.
  3. Choose -> Prod.Order.
  4. The production order network for the engine is displayed. The status CRTD is displayed in the System Status column for all production orders in the order network.

  5. Position the cursor on the top element, IAD-3000.
  6. To release the production order network, choose .
  7. The system status of all production orders changes from CRTD to REL.

  8. Choose .
  9. Make a note of the production order number.
  10. Choose until the overview tree appears.