Processing Material-Task List Assignments
Use
To use an inspection plan for inspecting materials, you must assign one or more materials to it.
Prerequisites
Procedure
The material-task list assignments overview screen appears.
Field |
What You Should Know |
Group counter |
You enter the group counter of the inspection plan, to which this material-task list assignment is to apply. |
Material |
You enter the material, to which this material-task list assignment is to apply. |
Plant |
You enter the plant for the material, to which this material-task list assignment is to apply. |
Field |
What You Should Know |
Vendor |
You can also make assignments that are based on a combination of material and vendor and/or a customer. If necessary, use the input help. |
Customer |
You can also make assignments that are based on a combination of material and vendor and/or a customer. If necessary, use the input help. |
When an inspection lot is created, the system calls the task list for inspecting a material that corresponds most closely to the material/task list allocation. The following hierarchy applies:
The system checks the assignments.
If there are no errors, the new assignments are added to the list of existing assignments.
The data record for the dependent characteristic specifications is deleted immediately, or on the key date for the change number, depending on whether you delete with a change number.
Result
The system writes all the data of your worklist to the database.