Perform Multi-Step Material Requirements Planning 
Use
You plan the material requirements for your plant Wichita. You determine the engine requirement deadlines and quantities. You plan on the basis of current material stocks, existing sales orders and expected requirements.
Procedure
Menu Path |
Logistics ® Production ® MRP ® Planning ® Single-Item, Multi-Level |
Transaction Code |
MD02 |
Field |
Data |
Material |
IAD-3000 |
Plant |
3600 |
Planning mode |
3 (Delete and recreate plan data) |
Also plan unchanged components |
Select |
Display material list |
Select |

Accept the default values for the other control parameters.
The multi-step engine requirements planning is performed.
The engine BOM is expanded in the requirements planning. The engine is listed in the first position with its components below.
You see the planning results based on the planned orders generated during MRP for the engine.
You can analyze the planned order in the dialog box.