Activating Availability Control 

Use

In the budget profile, you use the Activation type to specify whether and / or how the availability control is to be activated.

Features

There are three different types of activation:

If you selected background activation, you can activate the availability control online for a particular project.

Activities

When availability control is activated, the system does the following:

After activation, each posting to the project is checked by the availability control.

As availability control affects system performance, you should activate it in the background for projects with less detail, only when you think that the budget may be exceeded.