Usage
You have confirmed the actual dates on the activities. You can now evaluate the dates graphically in the project planning board. You can call up the project planning board either directly, or from the Project Builder.
Procedure
Menu Path |
From the Project node, choose Project Planning Board ® Change Project |
Transaction Code |
CJ2B |
Field |
Data |
Project def. |
I/# # # # |
Plan.board prf |
IT project |
w. activities |
Select |
The project planning board appears. The actual dates of the activities "Order Management Conception" and "Confirmation Module Conception" are displayed in a red date bar.
A dialog box appears.
Field |
Data |
Basic dates |
Select |
Actual dates |
Select |
Earliest dates |
Select |
The project planning board appears. In the diagram area, the system displays in a yellow date bar the actual dates from the confirmation of the activities 010 "Order Management Conception" and 0020 "Confirmation Module Conception".
To call up the legend for the project planning board, choose or Extras
® Legend.Result
You have now checked the planned and actual dates in the project planning board. You can now evaluate your project in the Project Information System.
Entering Activity Allocation