Usage
During the execution of the project, you record the project earned value by confirming the activities. The system uses the confirmed data to determine the actual costs and actual dates.
Prerequisites
You have
opened your project in the Project Builder and expanded it completely.Procedure
In the Work Area you see the detailed view of the network header.
You see an overview of the activities.
The Create Network Confirmation: Actual Data screen appears for activity 0010. In the network profile, we have defined that the FinalConf. indicator should be set automatically. The system copies the work center, the activity type, and the planned data from the network activity data.
Field |
Data |
Actual start |
Earliest scheduled start date |
Actual finish |
Earliest scheduled finish date |
Actual duration |
Planned duration from the activity |
Actual work |
Planned work from the activity |
You now see the confirmation data for activity 0020.
Field |
Data |
Actual start |
Earliest scheduled start date |
Actual finish |
Earliest scheduled finish date |
Actual duration |
Planned duration from the activity |
Actual work |
Planned work from the activity |
In the status line, the system displays an information message.
Result
The system uses the confirmation to determine the actual dates and the actual costs, before updating the values on the activity. The costs are totaled up within the project hierarchy. You can now evaluate the actual data in the project planning board.
Checking the Actual Dates