Editing Test Equipment 

Procedure

You assign one or more items of test equipment as production resources/tools (PRT), if you want to inspect with particular test equipment.

Use

You assign one or more items of test equipment to an operation or assign test equipment to an inspection characteristic, to determine the particular test equipment you want to use for the inspection.

Prerequisites

The used test equipment master data record must have been created and released in the system.

Procedure

  1. Choose Task Lists ® Production resources and tools.
  2. Copy into the context block the operation ID from that operation, to which you want to assign the test equipment.
  3. Enter a key date or a change number in the screen section Process using.
  4. Choose Create.
  5. A screen appears, in which you can select the required PRT-type.

  6. Select the required PRT-type and choose Continue.
  1. Enter on the tab page Material, Equipment, Document, Others, Dates all required data for the test equipment.
  1. Save the data.

The system writes all the data of your worklist to the database.

Additional Functions on the PRT Overview Screen

Function

Pushbutton/Menu Path

What You Should Know

Creating a production resource/tool

Create pushbutton

You can assign a new production resource/tool, if you entered an operation ID and a key date or a change number.

Changing a production resource/tool

Change/Lock pushbutton

You read the selected PRT data from the database into your worklist and therefore protect the data from being accessed by other users.

Displaying a production resource/tool

Display/Unlock pushbutton

You write the selected PRT data from your worklist to the database and therefore unlock the data for access by other users.

Copying a production resource/tool

Copy pushbutton

You can copy the data from the production resource/tool to use it in a different production resource/tool.

Deleting a production resource/tool

Delete pushbutton

You can delete the selected production resource/tools.

Printing production resource/tool

Print pushbutton

You can display the selected production resource/tools in a variable list and you can print this list.

Switch to first production resource/tool

First record pushbutton

If you selected several production resource/tools, you switch to the first production resource/tool, which was selected.

Switch to previous production resource/tool

Previous record pushbutton

If you selected several production resource/tools, you switch to the previous production resource/tool, which was selected.

Switch to next production resource/tool

Next record pushbutton

If you selected several production resource/tools, you switch to the next production resource/tool, which was selected.

Switch to last production resource/tool

Last record pushbutton

If you selected several production resource/tools, you switch to the last production resource/tool, which was selected.

Assigning materials to the task list

Task lists ® Material-task list assignment or double-click on the symbol for material

You go to the material-task list assignment, where you can assing one or several material(s) to the task list.

Switch to the task list header overview screen

Task Lists ® Header or double-click on the symbol for task list header

You switch to the task list header overview.

Switch to the operation overview screen

Task Lists ® Operations or double-click on the symbol for operation

You switch to the operation overview.

Switch to the inspection characteristics overview screen

Task Lists ® Inspection characteristics

Switch to the inspection characteristics overview screen.

Switch to the dependent characteristic specifications overview screen

Task Lists ® Dependent characteristic specifications or double-click on the symbol for inspection characteristic

You switch to the dependent characteristic specifications overview screen, where you can assign customer-, vendor- and/or material-specific inspection specifications to an inspection characteristic.

Displaying detail screen

Goto ® Details or double-click on the required row

You switch to the detail screen of the selected production resource/tool(s).

Displaying key date

Extras ® Key date

You can display the key date and change it, if necessary.

Displaying change number

Extras ® C hange number

You can display the change number and change it, if necessary.

Displaying effectivity parameters

Extras ® Effectivity parameters

You can display the effectivity parameters and change them, if necessary.

Displaying selection criteria

Extras ® Selection criteria details

You can display the chosen selection criteria.

Displaying work area

Extras ® Working area details

You can display the chosen working area.