Status by Period: Evaluation in Results Analysis
Scope of Functions
During execution of the functions for project results analysis, plan
results analysis, and project-related incoming orders, the system evaluates the status of the WBS elements to be processed. This is
necessary because these statuses determin the processing logic and valuation approach used.
Evaluation of the status information has changed for this release.
Background
The project results analysis and project-related incomingn order
functions are execute for each settlement period on the first day of
the following period. For processing by period, the system must
evaluate the status information for WBS elements as of the end of the settlement period.
Previously, the status evaluation took place as follows:
- For the results analysis function, by interpretation of status change documents
- For the project-related incoming orders function, when the function was executed
Status interpretation by period, however, was only possible if all the
status changes relevant to period-end closing had taken place in the closing period.
- In the case of the planned results analysis function, status evaluation
consists of an evaluation of the active actual status at the time of the program run.
These restrictions no longer apply with the new function Status Evaluation by Period in Results Analysis
.
Functions
- The date of the status change is recorded in a table. During status
interpretation, the system checks whether the status change took place during the closing period.
The Order accepted status is an exception. Here, the system uses
the date the SD order was entered, not the date the status changed.
- The new function allows you to overwrite the status change data
manually and online, backdating it, for example, to the closing period
if required. This makes it possible to take account of status changes made after the period end.
- For the first time, you can now enter data for planned status changes
for the planned results analysis function. This means you can determine the status of a WBS element by period in planning too.
- The function is supported for the following statuses:
Effects on Customizing
To this end, go the Project System IMG and choose Revenues and
Earnings -> Automatic and Periodic Allocations -> Activate Time Dependency of System Status.
See also
For more information on the Order accepted status, refer to the appropriate
release note.
For more information on period-end closing, refer to the release note on
Schedule Manager, the
Generalized Worklist
and in the SAP Library under Controlling -> Product Cost Controlling -> Cost Object Controlling.