Order Progress Report 
Description
The order progress report shows which documents, MRP elements, stocks
and deliveries exist for the products ordered by customers and their components. The order progress report provides:
- A quick overview of the status of production and procurement
- Information regarding the meeting or delaying of delivery dates
The functions are as follows:
- A hierarchical, expandable structure displays the data. All procurement
elements, stocks and deliveries for a product are displayed according
to the selection criteria. You can then explode the related component
structure for each internal procurement element. The existing elements are then determined and displayed for each component.
- Elements are displayed that are assigned to a sales order or WBS
element. Elements that were created manually and assigned to a sales
order or WSB element are also displayed. Elements without header material (for example, a purchase order for a service in external
processing) are displayed with a placeholder material, that is, the material field is empty.
- Only those elements and requirements are displayed that are specifically assigned to a sales order or WBS element from the
selection criteria, that is, elements that represent a customer stock
receipt or project stock receipt. Elements with collective stock receipts are not exploded further.
- The selected elements are displayed on the left of the report,
information regarding the elements on the right. The structure of the
right side is variable, depending on whether the material or element
fields are displayed. By using settings in Customizing, you can influence the presentation and content of the report.
- The following elements are displayed:
- Reservations, dependent requirements
- Deliveries, goods issues from SD view
- Customer sales stock, project stock
- Plant stock, goods receipts from MM view
- Purchase requisitions, purchase orders for external processing
- Colors are used to differentiate optically between element categories (see legend in the report).
- The time-related progress or time delay is determined and displayed for
each procurement element. In addition to time-related variances, variances in volume are also considered.
- The order progress report offers you various navigation options. You
can display or change each procurement element in the report, or
convert planned orders. In addition, it is possible, for example, to
branch directly into the requirements/stock list, MRP list and stock overview.
You can find additional information in the documentation 'PP - Production Orders' (PP-SFC) under section
Order Progress Report.
Change system parameters in customizing
You can enter pre-settings for the order progress report by using the following profiles:
Customizing production orders: Information System -> Profile for Order Progress Report -> Define Overall Profile
Customizing production orders: Information System -> Profile for
Order Progress Report -> Define Profile for Displayed Fields