QM: Enhancements in the Material Specification 
- In the past, you could not maintain different validity periods for the material specification
. As of Release 4.5A, you can specify a time reference for a material specification. This enhancement is based
on the solution used in an earlier release, in which a time reference was implemented for the material master.
You can still use the following transactions (which were already available in Release 3.0):
- QS61 (Maintain material specification)
- QS62 (Display material specification)
The validity period that you maintain or the system displays in these
transactions is the active one. This means that the system uses this
validity period, for example, when it creates an inspection lot or classifies a batch.
Release 4.5A provides the following transactions with which you can
plan a material specification for a specified key date or display the planned validity period for a key date:
In addition, Release 4.5A contains the following new transactions with
which you can activate the material specifications that have been planned for a specific key date:
- QS65 (Activate material specification, manual trigger)
- QS66 (Activate material specification, job planning)
- QS67 (Activate material specification, job overview)
You can access these transactions using the menu path Logistics ->
Quality management -> Quality planning -> Material and then Specification -> ...
- The functions for the material specification have been integrated in a table control
. All data that was previously displayed and maintained on a detail screen is now displayed in the table control.
- The function for unlocking master inspection characteristics was
previously only available for quantitative master inspection characteristics. You were able to change the tolerances for each
material. As of Release 4.5A, you can also use this function for
qualitative master inspection characteristics that reference a selected
set. In this way, you can store a material-specific selected set in the
material specification, other than the one that was planned in the
master inspection characteristic. As in the past, you can only use the
function for unlocking master inspection characteristics in the
material specification with master inspection characteristics that do not reference general characteristics in the batch class.
Further notes
You must execute transaction QS65 so the system will activate
the planned validity period for the material specification and use it
when it creates an inspection lot or classifies a batch. For this
reason, SAP recommends that you execute the report RQSPEZ10 assigned to
this transaction in a batch job (for example, once every day). This
ensures that the planned validity period for a material specification will be active on time.