In Release 4.5A, the material master includes a function for maintaining data at the new organizational level
MRP area. In the standard R/3 System, the pushbutton to access maintenance of MRP data at this
level is contained in the user department Material Requirements Planning (MRP)
. However, the pushbutton is visible only if your system administrator has activated the MRP areas for all of the client.
This is possible in Customizing for Material Requirements Planning in the activity
Activate MRP for MRP areas.
Note
MRP areas are defined in Customizing for Material Requirements Planning in the activity
Define MRP areas.
For more information, see: