| firm zone |
Delivery schedule time zone, defined in a scheduling agreement, determining the degree to which individual schedule lines represent binding orders, or commitments to purchase.
The firm zone is specified in days.
Example:
If the firm zone amounts to 20 days, all schedule lines whose delivery dates do not lie more than 20 calendar days in the future (calculated from the current date) are regarded as "firm" (that is to say, they count as fully binding orders, or purchase commitments). Should the orderer cancel such a schedule line, the vendor is entitled to invoice the buying entity for both material and production costs incurred in order to manufacture the relevant scheduled quantity.