Workforce Planning
Scope of Functions
In Release 4.6A the functionality and handling of workforce planning has been refined as follows:
- Assignment of Work not Restricted to People
It is now possible to assign activities not only to people but to the following personnel resources:
- Project teams for WBS elements
- Project Teams for WBS Elements
You can now form a project team for each WBS element. You can do this in:
- The project view of workforce planning
- The detail screen of the WBS element
When you distribute work in the project view the personnel resources are then proposed in the following order:
- The personnel resources that are assigned to the project team for the current WBS element
- The personnel resources that are assigned to the project team for a superior WBS element
- The personnel resources that are assigned to the work center for the relevant activity
- Assigning Other Personnel Resources
If you have set the Other personnel resources indicator in the
workforce planning profile, you can assign the activity personnel
resources, which are not assigned to either the work center or the project team for the WBS element.
- Selecting People using Qualifications
If an activity has a qualifications profile and qualifications have
been entered for the employees, you can produce a hit list in which the
employees are listed according to their qualifications for the task in question. You can then select an employee from this list.
As well as days, weeks, and months you can now also select posting periods, quarters
, and half-years as periods for displaying your data.
You can now work with mixed periods in workforce planning. To do so,
define the period split in the workforce planning profile and set the Mixed periods indicator.
- Displaying the Planned Work According to the Distribution Key
In the project view you can display the work planned for an activity
spread over the duration according to the distribution key in the
activity. If the activity does not have a distribution key, the System distributes the work equally over the duration.
- Rescheduling Work that has been Distributed
If the dates in a network change and you have already distributed the
work in workforce planning, you can decide (see Customizing), how to
proceed with the distributed work that lies outside the new activity dates. The system can:
- Redistribute the work according to the old distribution
- Distribute it to the start or finish of the rescheduled activity
In the new reporting transaction, you can obtain an overview about the
assignments and the distributed work. You can do this at the project
level or the work center level as well as for indivdual personnel resources.
Using standard ALV functions you can print a work distribution, send it to another user, or save it on your PC.
Effects on Customizing
New configuration possibilities for the new functions have been added to Customizing for the Project System under
Capacities-> Define Profile for Workforce Planning.
You can determine how the system reschedules work that has already been been distributed in
Dates -> Scheduling -> Define Scheduling Parameters for Networks
See also
For more information, see the SAP Library under Project System -> Capacity Planning.