Cost Estimate Without Quantity Structure: Process Flow 

Use

You can create a cost estimate without quantity structure for a material that does not yet have a PP quantity structure. For such materials, you create a quantity structure using a unit cost estimate.

Integration

You can also use existing R/3 data for material cost estimates without quantity structure, data such as materials, internal activities, work centers, material cost estimates, and base planning objects.

Prerequisites

You have checked the settings in the costing variant. For more information, see Preparing for Material Costing.

Features

  1. You create a material cost estimate without quantity structure using a costing variant as the basis for costing.
  2. For more information, see Creating a Cost Estimate Without Quantity Structure.

  3. You enter the costing data manually using the unit cost estimate.

For further information, see the following:

As an alternative to single-level unit costing, you can edit the cost estimate without quantity structure on a multilevel basis. For more information, see Multilevel Unit Costing.

  1. The system determines the prices for materials and internal activities as well as overhead and process costs.

For further information, see the following:

  1. You analyze the results and save the cost estimate.

For further information, see the following:

  1. You can update the costing results in the material master record, and transfer them into Profitability Analysis.

For further information, see the following:

  1. You can archive and delete material cost estimates.